Green Mountain Contractors, contracted through the City of Worcester will be installing cured-in-place-pipe (CIPP) at the following locations on the following dates:
- Stafford Street, Thursday, February 16, Tuesday, February 21 and Wednesday, February 22.
- Saint Nicholas Avenue, Wednesday, February 22
- Uncatena Avenue, Thursday, February 23
- Rowena Street, Thursday, February 23
- Pocasset Avenue on Friday, February, 24
- Uncatena Avenue on Friday, February 24.