For Immediate Release: 4/11/2023 9:43 am
Green Mountain’s excavation subcontractor, GVC, will be starting open cut spot repairs the week beginning Monday, April 10th. They plan to perform the open cut spot repairs in the following locations:
• Franklin Street
• Heard Street
• Acushnet Ave
• Cataumet Street
• Darrow Street
Green Mountain is scheduled to install cured-in-place pipe (CIPP) with the following schedule:
• Prospect Street on Wednesday, April 12th and Thursday, April 13th
Inland Waters’ short liner crew will be installing short liners Monday, April 10th through Wednesday, April 12th.
• 310 Belmont Street
• Hulbert Street
• Linda Vista Street