For Immediate Release: 7/30/2024 4:28 pm
WORCESTER, Mass. – Detours associated with construction on Highland Street have been modified based on the anticipated construction sequence and traffic patterns. The eastbound lane of Highland Street will be closed from 8 a.m. to 5 p.m. between Newton Square and Park Avenue until Friday, Aug. 23.
During the closure, westbound traffic will continue to use the roadway as normal while eastbound traffic will be redirected at Newton Square to travel on Pleasant Street to Park Avenue. Traffic signal timing has been adjusted at the intersection of Park Avenue and Pleasant Street to help accommodate detoured traffic, but drivers should expect congested conditions during peak traffic periods. During this time, motorists are strongly encouraged to seek alternate routes.
Local traffic will be able to access their residences by using the open westbound lane of Highland Street or by using Institute Road. The closure is to allow the public utility company Eversource to complete gas main replacement.