PUBLIC WORKS COMMITTEE

NOVEMBER 29, 2005

COUNCIL CHAMBER

Convened: 6:16 p.m.

Adjourned: 7:02 p.m.

 

Present were:      Chairperson Councilor Paul P. Clancy, Jr.

                             Councilor Philip P. Palmieri

                             Councilor Frederick C. Rushton @6:23 p.m.

 

Also:                    DPW Staffperson Matthew Labovites

                             DPW Staffperson Paul Moosey

                             DPW Staffperson Timothy Reiner

                             City Clerk David J. Rushford, clerk

 

HEARING

 

STREET TO MAKE PUBLIC

 

FIRST HEARING

FAVOR

OPPOSED

ABUTTERS

 

1.     Kelsey Dr.

Recommend Approval

 

4

0

12

 

MISCELLANEOUS

 

2.        Petition of Councillor Frederick Rushton on behalf of Barbara Miller request to repair or replace the culvert on Sherer Trail.

          #5 CC February 1, 2005

Recommend Approval of the replacement of the culvert

 

3.       Petition of Gina Greenleaf et al request the City of Worcester relocate/alter the terminus of Russell Calvin Dr. so that Russell Calvin Dr. and Taj Dr. become a dead end and that traffic does not pass between these two streets.

          #59 CC November 1, 2005

Recommend Hold (invite all property owners on Russell Calvin Drive the next time this is heard)

 

4.       Communication of the City Manager relative to refiling special legislation to allow a balloon payment option for private to public street conversion.

#23E CM April 5, 2005

          In Committee November 16, 2005 – Held

Recommend Re-filing of legislation with the Great and General Court to allow for a balloon payment option for private street conversion

 

5.       Communication of the City Manager relative to the conversion of private streets to public streets.

          #23F CM July 19, 2005

          In Committee November 16, 2005 – Held

Recommend File

 

6.       Communication of the City Manager relative to the feasibility of expanding North Lake Avenue to include sidewalks in conjunction with the street resurfacing project.

          #12B CM August 16, 2005

          In Committee November 16, 2005 – Held

Recommend File

 

7.       Communication of the City Manager relative to the Washington Sq. roundabout project.

          #11A CM September 6, 2005

          In Committee November 16, 2005 – Held

Recommend File

 

8.       Communication of the City Manager relative to Overgrowth Encroaching into the Public Way.

          #12B CM September 6, 2005

          In Committee November 16, 2005 – Held

Recommend File

 

9.       Communication of the City Manager relative to recommended changes in downtown and arterial parking restrictions to enhance the current street sweeping program.

          #12A CM September 27, 2005

          In Committee November 16, 2005 – Held

Recommend Hold

 

10.     Communication of the City Manager relative to storm damaged, impassable private streets.

          #12C CM October 25, 2005

          In Committee November 16, 2005 – Held

Recommend File

 

11.     Communication of the City Manager recommending the current apportionment from the Commonwealth of Massachusetts in the amount of Two Million Four Hundred Sixty Five Thousand Three Hundred Sixty Nine Dollars ($2,465,369.00) be appropriated to Account #41C440, DPW Street Resurfacing, to provide funding for current and future street resurfacing obligations.

In City Council October 25, 2005 #33G CM Order adopted 11-0 – Also referred to Public Works Committee for informational purposes

          In Committee November 16, 2005 – Held

Recommend File

 

Chairman’s Orders:

 

1.     Request the City Manager request the Commissioner of Public Works to provide the City Council with options for the construction of a cul-de-sac on Russell Calvin Drive in the vicinity of it’s current intersection with Taj Drive.

2.     Request the City Manager request the Commissioner of Public Works to provide the City Council with layouts of the following dead-ended streets: Forkey Avenue and Laurelwood Drive.

3.     Request the City Manager request the Commissioner of Public Works to provide the City Council with plans for Mulberry Street pocket park and the re-location of the Cristoforo Colombo statue.

4.     Request the City Manager request the Commissioner of Public Works provide the City Council with a complete listing of public and private streets that were addressed as a result of the October 2005 flooding.