Petitioner’s Name Location In City Council
1. Councillor
Clancy Brierway Dr. #25 CC 8/12/03
2. Councillor
Clancy Wabash Ave. #30 CC 8/12/03
(from Holcombe St to Koping St.)
3. Raymond
Mariano, Tacoma St. #37 CC 8/12/03
Exec. Dir. of WHA
(from Boylston St to 285 Tacoma St.)
4. Raymond
Mariano, Great Brook Valley Ave. #38 CC 8/12/03
Exec. Dir. of WHA
5. Raymond
Mariano, Brookview Dr. #39 CC 8/12/03
Exec. Dir. of WHA
6. Raymond
Mariano, Haven Lane #10 CC 9/16/03
Exec. Dir. of WHA
7. Councillor
Clancy Raymond St. #16 CC 9/9/03
8. Councillor
Palmieri Lake
Ave North #28 CC 9/9/03
9. Councillor
Palmieri Natural
History Dr. #28 CC 9/9/03
10. Petition of John MacKoul and Bailin & Associates,
Inc. request to extend the sanitary sewer in Salisbury St. beginning
approximately 100 ft. northerly of Whisper Dr. and continuing northerly for a
distance of approximately 1,500 ft. at petitioners expense.
#32 CC August 12, 2003
11. Petition of Jordan Robbins
et al request City eliminate standing water in street gutter on westerly
side of Kinnicutt Rd. South
which starts at 17 Kinnicutt Rd. South and continues north towards Amherst St.
#44 CC July 16,
2002
Chairman’s Order request the City Manager report to the City Council as to the feasibility and cost of lowering the drains and other public works appurtenances in Mabelle Street and Kinnicutt Avenue South.
12.
Communication of the City Manager
relative to North Parkway.
#23E CM September 9, 2003
DISCUSSION
ITEM – Lane
Markings on Lake Avenue
Chairman’s Resolution that the City Council hereby approves in concept of the proposed alterations to north and southbound lane markings in Lake Avenue between Sherbrook Avenue and Coburn Avenue including the elimination of one lane of traffic in some areas, the creation of a bike pathway and the installation of on-street parking in the vicinity of the Buffone Skating Arena (attached plan).